Under construction
QN GREENS PHASE 1
by QUALITAS NAMAN HOME MAKERS LLP
1/3, 1/4, 1/5, 1/7, Panvel, 410208
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2019, now proposed Dec 2021 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 81.1%.
Official RERA facts
- Registration
- P52000007707
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2021originally December 2019
- Construction
- 81.1% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000039573011 May 2023VALLARI WAMAN JATHAR vs Rajesh ShahWithdrwal order 395730.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Building & registration
- RERA registered
- Aug 2017
- Floors
- 6
Buyer community
Connect with other buyers and owners of QN GREENS PHASE 1 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching QN GREENS PHASE 1. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.