Jun 2023
Possession
27.3%
Built
0
Complaints
42
Units
High risk
- Possession delayed ~3 yrs. Originally promised Dec 2019, now proposed Jun 2023 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 27.3%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.
Official RERA facts
- Registration
- P52000008366
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2023originally December 2019
- Construction
- 27.3% complete
- Units sold
- 0 of 42
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 9
- Unit mix
- 42 res ยท 0 comm
- Architect
- VINOD TANDON
Buyer community
Connect with other buyers and owners of AADAR DEVELOPERS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching AADAR DEVELOPERS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.