Under construction

KUM KUM BHAGYA

by KUM KUM ENTERPRISES

S. NO. 22, H. NO. 4A1, PLOT NO. 1 AND 2, Bopele, 410201

Sept 2020
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Mar 2019, now proposed Sept 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Sept 2020) has passed with construction at 81.8%.

Official RERA facts

Registration
P52000009221
Status
Ongoing
Stage
Certificate Signed
Possession
September 2020originally March 2019
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of KUM KUM BHAGYA โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching KUM KUM BHAGYA. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.