Under construction

SAGAR SARGAM RESIDENCY

by Shree Tulsi Developes

Survey No 6, Hissa No. 5, Halivali Karjat, 410201

Mar 2027
Possession
71.6%
Built
0
Complaints
127
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52000009713
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally December 2024
Construction
71.6% complete
Units sold
48 of 127

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply75%
Sewerage (Chamber, Lines, Septic Tank , STP)75%
Landscaping & Tree Planting50%
Electrical meter room, sub-station, receiving station75%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
8
Unit mix
123 res ยท 4 comm

Buyer community

Connect with other buyers and owners of SAGAR SARGAM RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAGAR SARGAM RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.