Under construction

Cluster G

by Shibam Associates

S.no. 404/16 to 404/22 to S.No. 405/19 to 405/24 to 26, Neral, 410101

May 2022
Possession
56.8%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (May 2022) has passed with construction at 56.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2022 per the RERA filing.

Official RERA facts

Registration
P52000009953
Status
Ongoing
Stage
Certificate Signed
Possession
May 2022
Construction
56.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
6

Buyer community

Connect with other buyers and owners of Cluster G โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Cluster G. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.