ROYAL RESIDENCY

by Royal Enterprises

Survey no 32, Hissa No2A,CTS No 2236, TAKAI, 410203

Mar 2027
Possession
45.2%
Built
0
Complaints
133
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Mar 2024, now proposed Mar 2027 per the RERA filing.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 45.2%.

Official RERA facts

Registration
P52000011059
Status
Ongoing
Stage
Certificate Signed
Possession
March 2027originally March 2024
Construction
45.2% complete
Units sold
35 of 133

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Street Lightingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2017
Floors
6
Unit mix
133 res ยท 0 comm

Buyer community

Connect with other buyers and owners of ROYAL RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ROYAL RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.