Under construction

V M HERITAGE 2

by DILAWAR SUJATKHAN PATHAN

CTS 1048 SURVEY42/4, Khopoli, 410203

Jan 2020
Possession
33.6%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jan 2020) has passed with construction at 33.6%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jan 2020 per the RERA filing.

Official RERA facts

Registration
P52000011478
Status
Ongoing
Stage
Certificate Signed
Possession
January 2020originally July 2019
Construction
33.6% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started

Building & registration

RERA registered
Aug 2017
Floors
5

Buyer community

Connect with other buyers and owners of V M HERITAGE 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching V M HERITAGE 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.