ETERNIA
by GREENSCAPE DEVELOPERS PRIVATE LIMITED
PLOT NO 69 AND 70,SECTOR 20 AT KALAMBOLI, Panvel, 410218
- Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Mar 2027 per the RERA filing.
The airport-bet frontier โ golf course, hills and heavy new supply.
- Growth drivers:
- Navi Mumbai International Airport, MTHL access, NAINA planning zone.
- Who buys here:
- First-time buyers and investors betting on the airport economy.
PropPin area guide โ editorial, not a RERA disclosure.
Official RERA facts
- Registration
- P52000011766
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- March 2027originally December 2023
- Construction
- 90.9% complete
- Units sold
- 141 of 284
RERA complaint record1 record
- ComplaintCC1250463526 Dec 2025Atish Suresh Wagh vs GREENSCAPE DEVELOPERS PRIVATE LIMITED
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2017
- Floors
- 16
- Unit mix
- 258 res ยท 26 comm
- Architect
- SOYUZ TALIB ARCHITECTS PVT LTD
Buyer community
Connect with other buyers and owners of ETERNIA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ETERNIA. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.