THE AMBIENCE GARDEN

by MUKUND ARSS DEVELOPERS

3 AND 4, Uran, 400702

High risk
  • Possession delayed ~8 yrs. Originally promised Jun 2018, now proposed Jun 2026 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.7%.

Official RERA facts

Registration
P52000012153
Status
Ongoing
Stage
Certificate Signed
Possession
June 2026originally June 2018
Construction
90.7% complete
Units sold
96 of 140

RERA complaint record7 records

Complaint data not yet synced for this project.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting95%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Sept 2017
Floors
9
Unit mix
126 res ยท 14 comm

Buyer community

Connect with other buyers and owners of THE AMBIENCE GARDEN โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching THE AMBIENCE GARDEN. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.