All RERA projects
๐๏ธ
High risk
- Possession delayed ~8 yrs. Originally promised Jun 2018, now proposed Jun 2026 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 90.7%.
Official RERA facts
- Registration
- P52000012153
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2026originally June 2018
- Construction
- 90.7% complete
- Units sold
- 96 of 140
RERA complaint record7 records
Complaint data not yet synced for this project.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Planting95%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Building & registration
- RERA registered
- Sept 2017
- Floors
- 9
- Unit mix
- 126 res ยท 14 comm
Buyer community
Connect with other buyers and owners of THE AMBIENCE GARDEN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE AMBIENCE GARDEN. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.