Under construction

AAKRUTI BUILDING NO.2

by AAKRUTI BUILDERS & DEVELOPERS

15A2B1 AND 15A4,5A,6A AND 181,2,3 AND 191,2 AND 201,2,3,4 AND 21 AND 221,2,3,4 AND 3581A A, Pen (M Cl), 402107

Dec 2021
Possession
54.1%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 54.1%.

Official RERA facts

Registration
P52000012245
Status
Ongoing
Stage
Certificate Signed
Possession
December 2021
Construction
54.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsdone
Street Lightingdone
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposaldone
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Sept 2017
Floors
3

Buyer community

Connect with other buyers and owners of AAKRUTI BUILDING NO.2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AAKRUTI BUILDING NO.2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.