Under construction

ALIANA CITY PLAZA PHASE II

by IBRAHIM SULEMAN PATIL

CTS NO 1476 2189 2191 S NO 9A1B 9A1B1 9A3, Khopoli, 410203

Mar 2022
Possession
100%
Built
0
Complaints
0
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Jun 2019, now proposed Mar 2022 per the RERA filing.

Official RERA facts

Registration
P52000012269
Status
Ongoing
Stage
Certificate Signed
Possession
March 2022originally June 2019
Construction
100% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Sept 2017
Floors
2

Buyer community

Connect with other buyers and owners of ALIANA CITY PLAZA PHASE II โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ALIANA CITY PLAZA PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.