Under construction

AVAJ RESIDENCY

by AVAJ BUILDERS AND DEVELOPERS PRIVATE LIMITED

204, Vichumbe, 410206

Jun 2019
Possession
81.8%
Built
7
Complaints
0
Units
High risk
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Jun 2019) has passed with construction at 81.8%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2019 per the RERA filing.

Official RERA facts

Registration
P52000012402
Status
Ongoing
Stage
Certificate Signed
Possession
June 2019originally June 2018
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)35%
Storm Water Drains45%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station30%

Building & registration

RERA registered
Sept 2017
Floors
3

Buyer community

Connect with other buyers and owners of AVAJ RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AVAJ RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.