HARI OM NIRMAL

by HARI OM ENTERPRISE

C-22 C-23, Ulawe, 400706

Jun 2018
Possession
49.1%
Built
5
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2018) has passed with construction at 49.1%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2018 per the RERA filing.

Official RERA facts

Registration
P52000012709
Status
Ongoing
Stage
Certificate Signed
Possession
June 2018
Construction
49.1% complete
Units sold
0 of 0

RERA complaint record5 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started

Building & registration

RERA registered
Sept 2017
Floors
8

Buyer community

Connect with other buyers and owners of HARI OM NIRMAL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching HARI OM NIRMAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.