Legacy Vrindavan
by Concord Enterprises
17/1/A/3/A/2/B, 18/3/A/1 tO 10, 18/1/A, 18/1/B, 18/1/C, Karjat, 400075
High risk
- Possession delayed ~9 yrs. Originally promised Dec 2018, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000012969
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2018
- Construction
- 64.1% complete
- Units sold
- 14 of 98
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 19 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths70%
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lighting50%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposaldone
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacedone
Open Parkingdone
Building & registration
- RERA registered
- Sept 2017
- Floors
- 9
- Unit mix
- 98 res ยท 0 comm
Buyer community
Connect with other buyers and owners of Legacy Vrindavan โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Legacy Vrindavan. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 19 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.