Adhiraj Samyama Tower 1C

by Adhiraj Constructions Private Limited

Survey no 70 hissa no 1, Survey no 70 hissa no 2, -, 410208

Mar 2027
Possession
31.1%
Built
6
Complaints
262
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jul 2023, now proposed Mar 2027 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 31.1%.

Official RERA facts

Registration
P52000014859
Status
New
Stage
Certificate Signed
Possession
March 2027originally July 2023
Construction
31.1% complete
Units sold
230 of 262

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths72%
Water Supply28%
Sewerage (Chamber, Lines, Septic Tank , STP)78%
Storm Water Drains71%
Landscaping & Tree Planting52%
Street Lighting64%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting73%
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Jan 2018
Floors
46
Unit mix
262 res ยท 0 comm
Architect
Nitin Honawar

Buyer community

Connect with other buyers and owners of Adhiraj Samyama Tower 1C โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Adhiraj Samyama Tower 1C. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.