Under construction

SARTH APARTMENT BUILDING NO 2 PHASE I

by Y S Patil Builders and Developers

65/2, 66/1A, 66/1B, 66/2, KARJAT, 410201

Dec 2028
Possession
75.1%
Built
0
Complaints
91
Units
High risk
  • Possession delayed ~10 yrs. Originally promised Dec 2018, now proposed Dec 2028 per the RERA filing.

Official RERA facts

Registration
P52000015029
Status
New
Stage
Certificate Signed
Possession
December 2028originally December 2018
Construction
75.1% complete
Units sold
45 of 91

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains70%
Landscaping & Tree Planting30%
Street Lighting60%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving station50%
Open Parking70%

Building & registration

RERA registered
Jan 2018
Floors
9
Unit mix
91 res ยท 0 comm
Architect
VASTUKALP

Buyer community

Connect with other buyers and owners of SARTH APARTMENT BUILDING NO 2 PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SARTH APARTMENT BUILDING NO 2 PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.