AAROHI COMPLEX

by M/S TODAY SHYAM DEVELOPERS

PLOT NO 156, NAVI MUMBAI, 410208

Jul 2025
Possession
81.8%
Built
1
Complaints
147
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Nov 2022, now proposed Jul 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Jul 2025) has passed with construction at 81.8%.
Kharghar / PanvelValue

The airport-bet frontier โ€” golf course, hills and heavy new supply.

Growth drivers:
Navi Mumbai International Airport, MTHL access, NAINA planning zone.
Who buys here:
First-time buyers and investors betting on the airport economy.

PropPin area guide โ€” editorial, not a RERA disclosure.

Official RERA facts

Registration
P52000015331
Status
New
Stage
Certificate Signed
Possession
July 2025originally November 2022
Construction
81.8% complete
Units sold
48 of 147

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Feb 2018
Floors
9
Unit mix
133 res ยท 14 comm
Architect
DESTINATION ARCHITECTURE INTERIOR DESIGNS

Buyer community

Connect with other buyers and owners of AAROHI COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AAROHI COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.