High risk
- Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Sept 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000016251
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2026originally December 2022
- Construction
- 100% complete
- Units sold
- 26 of 28
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supply90%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waterdone
Water conservation /Rain water harvesting90%
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station90%
Building & registration
- RERA registered
- Apr 2018
- Floors
- 8
- Unit mix
- 28 res ยท 0 comm
- Architect
- Dessin Vinod Tandon
Buyer community
Connect with other buyers and owners of VAASTU ANKITA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VAASTU ANKITA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.