Mar 2027
Possession
73.2%
Built
0
Complaints
12
Units
High risk
- Possession delayed ~6 yrs. Originally promised Feb 2021, now proposed Mar 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000016310
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027originally February 2021
- Construction
- 73.2% complete
- Units sold
- 0 of 12
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parking5%
Building & registration
- RERA registered
- May 2018
- Floors
- 5
- Unit mix
- 12 res ยท 0 comm
Buyer community
Connect with other buyers and owners of BALAJI AANGAN โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching BALAJI AANGAN. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.