- Possession delayed ~3 yrs. Originally promised Dec 2024, now proposed Nov 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000018020
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2027originally December 2024
- Construction
- 46.4% complete
- Units sold
- 50 of 94
RERA complaint record2 records
- ComplaintCC1250319810 Sept 2025Himashree Kalita Singh vs RK GROUP OF INFRA
- ComplaintCC124009661 Dec 2024Rachna Sandeep Patil vs RK GROUP OF INFRALOPCC 12400966 (1).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Oct 2018
- Floors
- 21
- Unit mix
- 86 res ยท 8 comm
- Architect
- ATUL PATEL
Buyer community
Connect with other buyers and owners of VAISHNAVI EMPERIA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VAISHNAVI EMPERIA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.