PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

OPAL

by RSM HOMES LLP

PLOT NO 8 SECTOR 51 DRONAGIRI, TALUKA URAN, 400702

Dec 2023
Possession
90.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2023) has passed with construction at 90.5%.

Official RERA facts

Registration
P52000018118
Status
New
Stage
Certificate Signed
Possession
December 2023
Construction
90.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
BRANDED ELEVATOR OF BRAND KONE OR EQUIVALENT BRANDnot started

Building & registration

RERA registered
Oct 2018
Floors
8

Buyer community

Connect with other buyers and owners of OPAL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OPAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.