Under construction

GOKUL

by SUYASH BUILDERS AND DEVELOPERS

113/PART, PEN, 402107

Mar 2026
Possession
78.1%
Built
0
Complaints
245
Units
High risk
  • Possession delayed ~1 yr. Originally promised Oct 2024, now proposed Mar 2026 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2026) has passed with construction at 78.1%.

Official RERA facts

Registration
P52000018431
Status
New
Stage
Certificate Signed
Possession
March 2026originally October 2024
Construction
78.1% complete
Units sold
225 of 245

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)85%
Storm Water Drains85%
Landscaping & Tree Planting60%
Community Buildings75%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvesting25%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station85%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Others options to add more80%
Others80%

Building & registration

RERA registered
Nov 2018
Floors
16
Unit mix
232 res ยท 13 comm

Buyer community

Connect with other buyers and owners of GOKUL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching GOKUL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.