All RERA projects
๐๏ธ
Under construction
JUPITER HEIGHTS
SURVEY NO 185 HISSA NO 1 A, NEAR NEW ENGLISH HIGH SCHOOL, 410201
Dec 2026
Possession
15.2%
Built
0
Complaints
0
Units
High risk
- Behind schedule. Possession is due Dec 2026 but construction is only at 15.2%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000019352
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 15.2% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Jan 2019
- Floors
- 5
Buyer community
Connect with other buyers and owners of JUPITER HEIGHTS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching JUPITER HEIGHTS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.