Under construction

Renaissance Royal Phase 1

by Shree Sharada Infrastructures

303B, 303K, 581B, 591, 592A, 601, 602A2, 602A3, 602B, 602K, 602A1, 611, 612, Neral, 410101

Dec 2026
Possession
65.8%
Built
0
Complaints
216
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000019557
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2024
Construction
65.8% complete
Units sold
64 of 216

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supply20%
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drains80%
Landscaping & Tree Planting15%
Street Lighting40%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements30%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2019
Floors
8
Unit mix
216 res ยท 0 comm
Architect
Shree Sthapatya Associates

Buyer community

Connect with other buyers and owners of Renaissance Royal Phase 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Renaissance Royal Phase 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.