All RERA projects
๐๏ธ
Under construction
LAXMI RESIDENCY
by GURUDATTA BUILDERS AND DEVELOPERS LLP
554, PUSHPAK (NEW), 410206
Jun 2021
Possession
0%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2021) has passed with construction at 0%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2021 per the RERA filing.
Official RERA facts
- Registration
- P52000019760
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2021
- Construction
- 0% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2019
- Floors
- 6
Buyer community
Connect with other buyers and owners of LAXMI RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching LAXMI RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.