Under construction

VILLA OCEANO

by SHREEJI CREATIONS

PLOT NO 2, SECTOR 53, DRONAGIRI, Uran, 400707

High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2023, now proposed Dec 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 98.5%.

Official RERA facts

Registration
P52000019833
Status
New
Stage
Certificate Signed
Possession
December 2025originally June 2023
Construction
98.5% complete
Units sold
16 of 45

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station80%
Open Parkingnot started

Building & registration

RERA registered
Mar 2019
Floors
9
Unit mix
41 res ยท 4 comm

Buyer community

Connect with other buyers and owners of VILLA OCEANO โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VILLA OCEANO. Real notes from real buyers beat any brochure.

Start a discussion