Under construction

ANANDAM - PHASE I

by TODAY GLOBAL HOMES

PORTION OF LAND OUT OF GUT NO-1/3, 1/2/2, 1/6/A, 1/6/B, 1/6/C, 1/4, 2/2, 3/5/A, 3/5/B, 5/3 AND 111/1, ROHINJAN, 410210

Dec 2024
Possession
90%
Built
4
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.

Official RERA facts

Registration
P52000020292
Status
New
Stage
Certificate Signed
Possession
December 2024
Construction
90% complete
Units sold
0 of 0

RERA complaint record4 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Apr 2019
Floors
17

Buyer community

Connect with other buyers and owners of ANANDAM - PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANANDAM - PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.