All RERA projects
๐๏ธ
Under construction
ANANDAM - PHASE I
PORTION OF LAND OUT OF GUT NO-1/3, 1/2/2, 1/6/A, 1/6/B, 1/6/C, 1/4, 2/2, 3/5/A, 3/5/B, 5/3 AND 111/1, ROHINJAN, 410210
Dec 2024
Possession
90%
Built
4
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2024 per the RERA filing.
Official RERA facts
- Registration
- P52000020292
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 90% complete
- Units sold
- 0 of 0
RERA complaint record4 records
- ComplaintCC1260096722 Feb 2026Kanchan Pravin Madhavi vs TODAY GLOBAL HOMESFinal Order of Kanchan Madhavi.pdf on MahaRERA
- ComplaintCC1260084415 Feb 2026Leena Manoj Sachdeva vs TODAY GLOBAL HOMESFinal Order of Leena Sachdeva.pdf on MahaRERA
- ComplaintCC00600000059134729 Jul 2024sudip pandey vs Today Global DevelopersDisposal Order Sr No 44 signed.pdf on MahaRERA
- ComplaintCC00600000039792626 Dec 2023MANDAR MADHAV PIMPUTKAR vs TODAY GLOBAL DEVELOPERSOrder of Mandar Madhav Pimputkar.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Apr 2019
- Floors
- 17
Buyer community
Connect with other buyers and owners of ANANDAM - PHASE I โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching ANANDAM - PHASE I. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.