Wise City, South Block, Phase I,Plot RZ8 Building 5 Wing D5
by Wadhwa Construction and Infrastructure Private Limited
1156, 1157, 11713, 11714, Wadhwa Wise City, 410206
- Behind schedule. Possession is due Dec 2026 but construction is only at 27.3%.
- Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000020858
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2026
- Construction
- 27.3% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- May 2019
- Floors
- 26
Buyer community
Connect with other buyers and owners of Wise City, South Block, Phase I,Plot RZ8 Building 5 Wing D5 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Wise City, South Block, Phase I,Plot RZ8 Building 5 Wing D5. Real notes from real buyers beat any brochure.