Under construction
SKYLINE JEWEL
by UNIQUE SUPER INFRA PRIVATE LIMITED
PLOT NO 39 40, TALOJA (PHASE II), 410208
Jun 2021
Possession
90.9%
Built
1
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Jun 2021) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2021 per the RERA filing.
Official RERA facts
- Registration
- P52000021023
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2021
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record1 record
- ComplaintCC00600000050055929 May 2024unique super infra PVT LTD vs MR. DEVKUMAR MANDALOrder of Unique Infra - DFD.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- May 2019
- Floors
- 5
Buyer community
Connect with other buyers and owners of SKYLINE JEWEL โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SKYLINE JEWEL. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.