Jun 2028
Possession
58.2%
Built
0
Complaints
353
Units
Caution
- Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Jun 2028 per the RERA filing.
Official RERA facts
- Registration
- P52000021134
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2028originally December 2025
- Construction
- 58.2% complete
- Units sold
- 186 of 353
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths80%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Storm Water Drains50%
Landscaping & Tree Planting50%
Street Lighting50%
Water conservation /Rain water harvesting50%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Building & registration
- RERA registered
- Jun 2019
- Floors
- 9
- Unit mix
- 339 res ยท 14 comm
- Architect
- DESTINATION ARCHITETURE INTERIOR DESIGNS
Buyer community
Connect with other buyers and owners of THE ORBIS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching THE ORBIS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.