Under construction

Magnolia Cluster 2

by Wadhwa Construction and Infrastructure Private Limited

RZ-04-PART, Wise City, 410206

Dec 2026
Possession
41.2%
Built
0
Complaints
54
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 41.2%.
  • Promised amenities not started. Clubhouse is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000021142
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
41.2% complete
Units sold
39 of 54

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains95%
Landscaping & Tree Planting95%
Street Lighting75%
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationdone
Open Parkingnot started

Building & registration

RERA registered
Jun 2019
Floors
26
Unit mix
54 res ยท 0 comm
Architect
Visionary Design Architects

Buyer community

Connect with other buyers and owners of Magnolia Cluster 2 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Magnolia Cluster 2. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.