COMMANDERS HEERA SIDDHI HOMES PHASE III
SURVEY NO 16 HISSA 2, Panvel, 410220
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000023450
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2023
- Construction
- 39.4% complete
- Units sold
- 63 of 480
RERA complaint record2 records
- ComplaintCC1250259828 Jul 2025KALURAM SUKHDEV GAIKWAD vs MEGAPLEX PROPERTIES LLP
- ComplaintCC00600000040846928 Dec 2023Kaluram Sukhdev Gaikwad vs Jagdish Madhukar Chaudhari22.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Dec 2019
- Floors
- 9
- Unit mix
- 462 res ยท 18 comm
- Architect
- AR DHARMESH V BHALANI
Buyer community
Connect with other buyers and owners of COMMANDERS HEERA SIDDHI HOMES PHASE III โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching COMMANDERS HEERA SIDDHI HOMES PHASE III. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.