Under construction

ELEGANT PHASE - I

by DGAINS BHOOMI NIRMAAN LIMITED

262, HIREWADI, 410201

Dec 2026
Possession
58.9%
Built
0
Complaints
27
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000024571
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2023
Construction
58.9% complete
Units sold
13 of 27

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone
Open Parkingdone

Building & registration

RERA registered
Feb 2020
Floors
5
Unit mix
27 res ยท 0 comm
Architect
GIRISH GOHIL

Buyer community

Connect with other buyers and owners of ELEGANT PHASE - I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ELEGANT PHASE - I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.