PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Madhav CornerMahaRERA P52000025995

by Dolphin Developers

4914 S NO 14/1A/2, Katrang, 410203

Sept 2023
Possession
76.4%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2023) has passed with construction at 76.4%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2023 per the RERA filing.

Official RERA facts

Registration
P52000025995
Status
New
Stage
Certificate Signed
Possession
September 2023
Construction
76.4% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Aug 2020
Floors
6

Buyer community

Connect with other buyers and owners of Madhav Corner โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Madhav Corner. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.