PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

VAASTU SANKALPMahaRERA P52000026957

by VAASTU ENTEPRISES

SURVEY NO 168, AT PASHANE, 410101

Dec 2026
Possession
52.6%
Built
0
Complaints
97
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000026957
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2024
Construction
52.6% complete
Units sold
46 of 97

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Nov 2020
Floors
5
Unit mix
72 res ยท 25 comm
Architect
A AND K ASSOCIATES

Buyer community

Connect with other buyers and owners of VAASTU SANKALP โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VAASTU SANKALP. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.