AARSH BHANUDASMahaRERA P52000027508

by POONAM BHANUDAS MOKAL

PLOT NO -59, PUSHPAK NEW, 410206

Dec 2026
Possession
55.1%
Built
0
Complaints
19
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000027508
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2024
Construction
55.1% complete
Units sold
4 of 19

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)45%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2020
Floors
6
Unit mix
17 res ยท 2 comm
Architect
Atul Patel Architects

Buyer community

Connect with other buyers and owners of AARSH BHANUDAS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching AARSH BHANUDAS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.