City Of Music Phase IIIMahaRERA P52000027911

by Nirvana Leisure Realty

70/1A, 70/1B, 73/1A, 73/1B, 73/4, 73/5A, 75/1A/1, 75/1A/2,75/1B,78/1A, 78/1B, 76/1, 76/2, Khopoli, 410205

Dec 2026
Possession
โ€”
Built
1
Complaints
78
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Jun 2023, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000027911
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2023
Construction
โ€”
Units sold
68 of 78

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supply50%
Storm Water Drains30%
Landscaping & Tree Planting40%
Street Lighting30%
Community Buildings75%
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Space30%
Open Parking40%

Building & registration

RERA registered
Jan 2021
Architect
DEEPAK HIREMATH

Buyer community

Connect with other buyers and owners of City Of Music Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching City Of Music Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.