Under construction

Cityopia Bankers Enclave

by Cityopia Bankers Enclave Cooperative Housing Society Limited

Survey No -71 /1/A, Panvel, 410221

Caution
  • Possession delayed ~2 yrs. Originally promised Jun 2026, now proposed Jun 2028 per the RERA filing.

Official RERA facts

Registration
P52000028184
Status
New
Stage
Certificate Signed
Possession
June 2028originally June 2026
Construction
32.9% complete
Units sold
0 of 200

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2021
Floors
33
Unit mix
200 res ยท 0 comm

Buyer community

Connect with other buyers and owners of Cityopia Bankers Enclave โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Cityopia Bankers Enclave. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.