V M RESIDENCYMahaRERA P52000029118

by V M DEVELOPERS

251 CTS NO 1665 1668 SURVEY No 542 572, PLOT NO 25/1, CTS NO 1665 AND 1668. S NO 54/2 AND 57/2, 410203

Jul 2024
Possession
86.8%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jul 2024) has passed with construction at 86.8%.

Official RERA facts

Registration
P52000029118
Status
New
Stage
Certificate Signed
Possession
July 2024
Construction
86.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains80%
Water conservation /Rain water harvesting55%
Electrical meter room, sub-station, receiving station65%

Building & registration

RERA registered
Apr 2021
Floors
9

Buyer community

Connect with other buyers and owners of V M RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching V M RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.