PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Sai World Empire Phase IIIMahaRERA P52000029168

by paradisesuperstructures

Survey No 94/3A, 4, 102/5B, 5K, Rohinjan, 410210

Dec 2027
Possession
79.7%
Built
1
Complaints
672
Units
Caution
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P52000029168
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
79.7% complete
Units sold
230 of 672

RERA complaint record1 record

  • ComplaintSM1260042624 Jun 2026
    Bhakti Achrekar vs paradisesuperstructures

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths35%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)35%
Storm Water Drains20%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
May 2021
Floors
55
Unit mix
672 res ยท 0 comm
Architect
Hiten Sethi & Associates

Buyer community

Connect with other buyers and owners of Sai World Empire Phase III โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sai World Empire Phase III. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.