Under construction

OSCAR HEIGHTS

by OSCAR BUILDERS

CTS NO 54A,54B,55,56,57,58,67, AND FINAL PLOT 30 -A, PEN, 402107

Dec 2027
Possession
74.8%
Built
0
Complaints
245
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52000029513
Status
New
Stage
Certificate Signed
Possession
December 2027
Construction
74.8% complete
Units sold
117 of 245

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)60%
Community Buildings50%
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jun 2021
Floors
9
Unit mix
245 res ยท 0 comm
Architect
SACHIN GHARAT

Buyer community

Connect with other buyers and owners of OSCAR HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching OSCAR HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.