Under construction

UNIMAX PRIDEMahaRERA P52000031129

by MYCITY CONSTRUCTIONS LLP

SURVEY NO 6, GHOT VILLAGE, 410208

Dec 2026
Possession
78.8%
Built
0
Complaints
132
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000031129
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
78.8% complete
Units sold
72 of 132

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving station50%
Open Parkingnot started

Building & registration

RERA registered
Oct 2021
Floors
5
Unit mix
132 res ยท 0 comm
Architect
DEEPAK P. THAKARE ARCHITECTS AND PLANNERS

Buyer community

Connect with other buyers and owners of UNIMAX PRIDE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UNIMAX PRIDE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.