Under construction

Regents Park KhargharMahaRERA P52000031227

by METRO SATYAM DEVELOPERS

Survey no.13 1, 14 5B, 14 6, 15 5, 15 6, and 15 8, Rohinjan, 410208

Jun 2027
Possession
86.8%
Built
3
Complaints
477
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P52000031227
Status
New
Stage
Certificate Signed
Possession
June 2027
Construction
86.8% complete
Units sold
459 of 477

RERA complaint record3 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply80%
Sewerage (Chamber, Lines, Septic Tank , STP)95%
Storm Water Drains95%
Landscaping & Tree Planting25%
Treatment And Disposal Of Sewage And Sullage Water50%
Solid Waste Management And Disposal60%
Water conservation /Rain water harvestingdone
Energy managemcntnot started
Fire protection and fire safety requirements98%
Electrical meter room, sub-station, receiving station60%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2021
Floors
29
Unit mix
470 res ยท 7 comm
Architect
AN ARCH ARCHITECT & PLANNER

Buyer community

Connect with other buyers and owners of Regents Park Kharghar โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Regents Park Kharghar. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.