Under construction

PADMAVATI SHALIKMahaRERA P52000033132

by PADMAVATI DEVELOPERS

PLOT NO 74 SECTOR 25, NAVI MUMBAI, 410210

Jun 2023
Possession
37.5%
Built
0
Complaints
1
Units
High risk
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 37.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2023 per the RERA filing.

Official RERA facts

Registration
P52000033132
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
37.5% complete
Units sold
0 of 1

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Feb 2022
Floors
17

Buyer community

Connect with other buyers and owners of PADMAVATI SHALIK โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PADMAVATI SHALIK. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.