Under construction

Shreeji Kuber HomeMahaRERA P52000034767

by SHREEJI LIFESPACES REALTORS

F-17, Sector-08, 410206

May 2025
Possession
72.7%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (May 2025) has passed with construction at 72.7%.

Official RERA facts

Registration
P52000034767
Status
New
Stage
Certificate Signed
Possession
May 2025originally November 2024
Construction
72.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Apr 2022
Floors
3

Buyer community

Connect with other buyers and owners of Shreeji Kuber Home โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shreeji Kuber Home. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.