All RERA projects
๐๏ธ
Under construction
DELTA GREENSMahaRERA P52000034901
08, PUSHPAK NODE DAPOLI, 410206
Mar 2027
Possession
98.2%
Built
0
Complaints
151
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.
Official RERA facts
- Registration
- P52000034901
- Status
- New
- Stage
- Certificate Signed
- Possession
- March 2027
- Construction
- 98.2% complete
- Units sold
- 118 of 151
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)50%
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space20%
Building & registration
- RERA registered
- Apr 2022
- Floors
- 15
- Unit mix
- 128 res ยท 23 comm
- Architect
- SATISH V AHUJA AND ASSOCIATES
Buyer community
Connect with other buyers and owners of DELTA GREENS โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching DELTA GREENS. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.