Dec 2026
Possession
81.9%
Built
2
Complaints
451
Units
Caution
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000045234
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
81.9% complete
Units sold
294 of 451

RERA complaint record2 records

  • ComplaintCC1240129531 Dec 2024
    SATYAM INFRA REALTY LLP vs Mrs Nahid Saad Khan
  • ComplaintCC1240129731 Dec 2024
    SATYAM INFRA REALTY LLP vs Mrs Nahid Saad Khan

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supply70%
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains15%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvesting90%
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
May 2022
Floors
28
Unit mix
451 res ยท 0 comm

Buyer community

Connect with other buyers and owners of SATYAM TRINITY TOWERS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SATYAM TRINITY TOWERS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.