All RERA projects
๐๏ธ
Nov 2026
Possession
87.7%
Built
0
Complaints
188
Units
Caution
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Nov 2026 per the RERA filing.
Official RERA facts
- Registration
- P52000045608
- Status
- New
- Stage
- Certificate Signed
- Possession
- November 2026originally November 2025
- Construction
- 87.7% complete
- Units sold
- 84 of 188
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirements50%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingdone
Building & registration
- RERA registered
- May 2022
- Floors
- 11
- Unit mix
- 165 res ยท 23 comm
- Architect
- Satish Manohar
Buyer community
Connect with other buyers and owners of Balaji Tulips โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Balaji Tulips. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.