MAZAGON DOCK NIVARA CO-OP. HSG. SOC. LTD.MahaRERA P52000047201

by MAZAGON DOCK NIVARA CO-OP HSG SOC LTD

Plot 3 Sub Plot J, New Panvel (W), 410206

Mar 2027
Possession
83.6%
Built
0
Complaints
77
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Sept 2024, now proposed Mar 2027 per the RERA filing.

Official RERA facts

Registration
P52000047201
Status
New
Stage
Certificate Signed
Possession
March 2027originally September 2024
Construction
83.6% complete
Units sold
50 of 77

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Storm Water Drains90%
Landscaping & Tree Planting50%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements80%
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Oct 2022
Floors
15
Unit mix
77 res ยท 0 comm
Architect
DESTINATION ARCHITECTURE INTERIOR DESIGNS

Buyer community

Connect with other buyers and owners of MAZAGON DOCK NIVARA CO-OP. HSG. SOC. LTD. โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAZAGON DOCK NIVARA CO-OP. HSG. SOC. LTD.. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.