Vista HeightsMahaRERA P52000047480

by Mahendra Tambaram Patel

Plot No. 14A, Sector - 18, Ulwe, 410206

Dec 2026
Possession
39.5%
Built
1
Complaints
0
Units
High risk
  • Possession delayed ~1 yr. Originally promised Oct 2025, now proposed Dec 2026 per the RERA filing.
  • Behind schedule. Possession is due Dec 2026 but construction is only at 39.5%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P52000047480
Status
New
Stage
Certificate Signed
Possession
December 2026originally October 2025
Construction
39.5% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parking2%

Building & registration

RERA registered
Nov 2022
Floors
5

Buyer community

Connect with other buyers and owners of Vista Heights โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vista Heights. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.